Data Centre glossary
The vocabulary of the Data Centre layer.
Plain definitions of the terms that appear in facility designs, commissioning reports and colocation contracts, written for the people who finance and operate the buildings that AI hardware runs in.
The terms are in four groups, from the site and the shell through the power train and the cooling plant to the way a finished facility is tested, run and sold. Each definition is written for owners, operators and investors who need to read a basis of design, a Tier claim or a lease schedule with a critical eye. Where a term bears directly on the cost or the capacity of an AI facility, the definition says how, and where an accelerator workload changes the conventional answer, the definition says that too.
Groups follow the order in which a facility is conceived, built and sold. Site and shell terms describe what is built and to what standard, the power train describes how electricity reaches the rack, cooling describes how heat leaves it, and operations and commercial terms describe how the finished capacity is proven, kept running and contracted.
Part of the Data Centre layer. All glossaries
Group 01
Site, shell and design
A facility's shape is fixed early and is expensive to change. The density it is designed for, the split of its floor between halls and plant, and the resilience standard it is built to decide what it can host and what it can be sold for over a working life of twenty years or more.
- Campus
A site holding several data centre buildings that share a boundary fence, an intake substation, security, roads and fibre entries, usually with land reserved for more. The shared substation matters most: a grid connection takes years to secure, and each new building reuses one negotiated once. For an investor a campus is a pipeline of phases, and its spare land is worth what remains unallocated of the connection.
Show in diagramHide diagram
The reserved land and the shared intake substation. The second building reuses a grid connection negotiated once. See also Utility intake, Phased delivery, Planning and permitting
- Data hall
A single room within a data centre building that holds rows of racks, with its own power distribution, cooling and access control. Halls let capacity be fitted out, sold and maintained in portions and contain a fault to one room. Hall size follows the capacity block the owner expects to sell, and AI tenants increasingly take whole halls to keep the links between racks short.
Show in diagramHide diagram
Two halls, each with its own distribution and cooling, so a fault in one is contained. See also White space, Grey space, Wholesale and hyperscale colocation
- White space
The floor area of a data hall available for racks, measured in square metres and sold by the kilowatt. It covers the aisles as well as the rack footprints, since containment and service access are usable floor. White space is the smallest share of a modern facility's built area, and as density rises the plant per square metre grows, so a large white space beside a small plant area marks a low-density facility.
Show in diagramHide diagram
The hatched floor inside each hall: rack footprints and aisles, the only area that earns rent. See also Grey space, Design density, Data hall
- Grey space
The parts of a building that house the plant serving the halls: switchrooms, UPS and battery rooms, generator enclosures, chiller and pump rooms, water treatment and fuel storage. It earns no revenue directly, and its share rises with density and redundancy, since a 2N topology doubles most electrical rooms. In a high-density AI facility it and the plant yard can occupy more area than the halls.
Show in diagramHide diagram
Switchrooms, UPS rooms and pump rooms around the halls. In a 2N design most of these rooms appear twice. See also White space, Redundancy topology, Uninterruptible power supply
- Powered shell
A building delivered with its structure, envelope, utility connection and often its medium-voltage intake, but without the UPS, generators, cooling plant and distribution that make a hall usable. The tenant installs the fit-out to its own design at its own cost. The lease is priced on the building and the power allocation, and suits a hyperscale tenant with its own engineering standards, which holds most of the equipment at the end of the term.
Show in diagramHide diagram
What a powered shell delivers: the building, the intake and the substation, with the grey space and the halls left empty for the tenant. See also Turnkey, Build-to-suit, Wholesale and hyperscale colocation
- Turnkey
A hall delivered complete to the rack position, with power, cooling, fire protection, security and monitoring installed, commissioned and operated by the landlord. The tenant brings its IT equipment and takes service on a committed capacity. Most colocation is sold this way, and the landlord's return rests on fit-out cost per kilowatt and on the hall staying lettable after the first tenant leaves, harder when the fit-out was tuned to one tenant.
See also Powered shell, Retail colocation, Design density
- Build-to-suit
A facility designed and built for one named tenant, to its specification, under a lease agreed before construction starts. The tenant gets the density, resilience and layout it wants; the developer gets a pre-let for construction finance. Specificity is the risk: a hall built for one tenant's liquid-cooling standard and rack weight may need reworking for the next, so lease term and residual value assumptions carry more weight than in a speculative build.
See also Powered shell, Take-or-pay, Decommissioning and refresh
- IT loadCritical load
The electrical power drawn by the computing equipment itself, measured at the rack or the UPS output, and the quantity in which capacity is designed, sold and reported. A facility described as 100 MW usually means 100 MW of IT load, though the measurement point should be asked for. IT load excludes cooling, lighting and electrical losses, so the grid connection must be larger by the overhead PUE describes.
Show in diagramHide diagram
The meter at the UPS output and the meter at the rack. A facility's IT load is usually quoted at the first; the second is what the tenant draws. See also Facility load, Power usage effectiveness, Pricing units
- Facility load
The total electrical demand of the building: IT load plus cooling, pumps, fans, UPS and transformer losses, lighting and offices. It is what the grid connection, generators and intake switchgear must carry, and it sets the connection application and the energy bill. A design quoting IT capacity without facility load has not said how much grid power it needs; the ratio between the two moves with climate, density and cooling method.
Show in diagramHide diagram
Facility load: IT design capacity plus the overhead band of cooling, pumps, fans and losses. See also IT load, Utility intake, Power usage effectiveness
- Design densitykW per rack
The IT load a hall is engineered to supply and cool per rack, stated in kilowatts per rack or per square metre of white space. Enterprise halls were built for a few kilowatts per rack; current accelerator racks draw well over 100 kW each, and plant sized for one cannot serve the other. Density most determines whether a facility can host AI hardware, and a megawatt figure says nothing about it.
Show in diagramHide diagram
The IT design bar at a given density. Doubling design density halves the white space the same bar needs, and changes every bar below it. See also Rack, Liquid cooling, Structural loading
- Rack
The standard steel frame that holds servers, switches and power strips, 19 inches wide at the equipment faceplate and measured in rack units of 44.45 mm, with 42 to 48 units the common height. It is the unit of occupancy in retail colocation and of density. Accelerator systems now ship as complete racks with coolant manifolds and busbars, often wider, deeper and well over a tonne, changing floor loading, aisle widths and lifting equipment.
See also Design density, Structural loading, Hot aisle and cold aisle containment
- Hot aisle and cold aisle containment
Racks facing each other across a cold aisle that receives supply air and exhausting into a hot aisle behind, with doors and panels sealing one aisle so the two air streams cannot mix. Containment lets supply air be delivered warmer and returned hotter, raising plant efficiency and capacity. It is the cheapest upgrade in an air-cooled hall and still needed around liquid-cooled racks, which reject a share of their heat to air.
Show in diagramHide diagram
The contained cold aisle and hot aisle. Containment is what keeps the two air streams at their two temperatures. See also Supply and return temperatures, Delta T, CRAC and CRAH units
- Raised floor and slab
Two ways of building a hall floor. A raised floor on pedestals above the slab creates a plenum for supply air, cabling and pipework beneath the tiles; a slab hall distributes air, power and liquid overhead. Raised floors were the default for decades, but heavy accelerator racks can exceed their load rating, and a plenum adds little once cooling is liquid. New high-density halls are mostly slab with overhead busway, cable tray and coolant pipework.
See also Structural loading, Busway, Liquid cooling
- Structural loading
The weight a floor, and the ground or building beneath it, is designed to carry, stated as a distributed load in kilopascals and as point loads under rack castors and feet. A liquid-cooled accelerator rack can weigh well over a tonne on less than a square metre, and its route from the loading dock must carry the same. Upper floors, raised floors and older slabs often cannot, so many AI deployments go to single-storey slab halls.
See also Rack, Raised floor and slab, Decommissioning and refresh
- Planning and permitting
The approvals a facility needs before and during construction: land use and development consent, environmental assessment, building permits, and licences for generator emissions, noise, water discharge and fuel storage. Each sits with a different authority on its own timetable, and generators are the usual friction, being a sizeable combustion plant. Approvals are a schedule risk on a par with the grid connection, so a site with consents in hand is worth more.
Show in diagramHide diagram
The first stage, and the one with the most authorities on its critical path. See also Standby generator, Campus, Cooling tower
- Modular and prefabricated construction
Electrical rooms, cooling plant and sometimes whole halls built as factory-assembled modules, tested, shipped and connected on site. Prefabrication shortens the site programme, moves skilled labour into a factory, and lets a design repeat with the same drawings and commissioning scripts. It suits phased delivery and standardised power blocks; its limits are transport dimensions, module interfaces, and a module built for one density being as fixed as a room.
Show in diagramHide diagram
Prefabrication shortens the construction stage and lets levels 1 and 2 be completed in the factory. See also Phased delivery, Commissioning levels, Design density
- Phased delivery
Bringing capacity into service in stages, each with its own halls, power blocks and cooling plant, rather than building the full design at once. Phasing matches capital spend to signed demand and lets later phases adopt newer density and cooling designs. The shared intake, fibre entries and site services must be sized for the end state on day one, so a phased project carries deliberate idle capacity in its first years.
Show in diagramHide diagram
Three phases sharing one intake sized for all of them on day one. See also Campus, Utility intake, Ramp schedule
- Tier classificationUptime Institute Tier
A four-level Uptime Institute standard describing a facility's topology. Tier I has a single path with no redundancy, Tier II adds redundant components, Tier III is concurrently maintainable, and Tier IV is fault tolerant. Certification is issued separately for design, the built facility and operations, so a Tier III design claim describes drawings until the building is certified, and Tier III equivalent has no standing. A Tier does not certify an availability percentage, a location or a cooling method.
Show in diagramHide diagram
Tier I is a single path at N. Each higher Tier adds what the diagrams to the right show: spare components, then a second path, then separation between the paths. See also Concurrent maintainability, Fault tolerance, TIA-942
- TIA-942
A telecommunications industry standard, ANSI/TIA-942, setting requirements for data centre sites, structure, electrical and mechanical systems and cabling, with four resilience ratings. The ratings resemble the Uptime Tiers but are assessed by third-party auditors against a published checklist, and the two schemes are separate. TIA-942 is more prescriptive about the building and cabling, a facility may be rated under one scheme, both or neither, and the rating body should be stated.
See also Tier classification, Fibre entry, Certifications
- Concurrent maintainability
The property, required for Tier III, that every capacity component and distribution path can be taken out of service for planned work without interrupting the IT load. It needs redundant components and at least two distribution paths, one possibly passive. It lets an operator honour a maintenance regime for twenty years without a planned outage, and most AI tenants require it, since a planned shutdown loses a training run as surely as a fault.
Show in diagramHide diagram
Concurrent maintainability drawn as 2N: the whole left system is out for maintenance and the load has not noticed. See also Tier classification, Maintenance regime, Redundancy topology
- Fault tolerance
The property, required for Tier IV, that any single unplanned failure of a component, a distribution path or a fire or water compartment leaves the IT load running. It needs multiple active distribution paths, compartmentalisation between redundant systems and continuous cooling through a power transfer. It roughly doubles the plant of a concurrently maintainable design, and its market is narrower than its reputation, because most AI workloads checkpoint and a rare short outage costs less than Tier IV.
Show in diagramHide diagram
Fault tolerance needs the 2N drawing plus a wall between the two systems, so that one fire or flood cannot reach both. See also Tier classification, Concurrent maintainability, A and B feeds
Group 02
Power train inside the building
The power train is the largest share of a facility's capital cost and the source of most serious outages. How it is sized and duplicated decides the capacity that can be sold, the cost per kilowatt of delivering it, and how a hall behaves when an accelerator cluster steps its draw by a large fraction within a second.
- Utility intake
The point where the grid supply enters the facility's ownership: the intake switchroom or substation that receives, meters and passes the feeders to the medium-voltage switchgear. The Power layer ends here and the Data Centre layer begins. A resilient facility takes two feeders, ideally from different upstream substations, and sizes the intake for the end-state load from the first phase, since enlarging it later means a second connection.
Show in diagramHide diagram
Two feeders enter at the intake. The Power layer ends at the meter on each; everything to the right is the Data Centre layer. See also Medium-voltage switchgear, Facility load, Phased delivery
- Medium-voltage switchgearMV switchgear
Switching and protection equipment at the distribution voltages inside a large facility, typically 11 kV to 33 kV, routing power from the intake to the transformers and isolating faults. It is built as lineups of circuit breakers and protection relays, with bus ties that let one intake feed both halves of a 2N design. Lead times now rival transformers', and the choice between air-insulated and gas-insulated designs is constrained by floor area and sulphur hexafluoride restrictions.
Show in diagramHide diagram
The MV lineups and the bus tie between them. Closing the tie lets one intake feed both paths. See also Utility intake, Transformer, Arc flash
- Transformer
A static device that steps voltage down, in a data centre from medium-voltage distribution to the low voltage at which UPS systems and switchboards operate. Transformers are rated in kilovolt-amperes, sited outdoors as oil-filled or indoors as dry-type units, and their losses count against efficiency every hour. They are now among the longest-lead items in a build, and high-density designs push medium voltage closer to the hall to shorten heavy low-voltage runs.
Show in diagramHide diagram
One transformer per path steps medium voltage to 400 V. Its losses run every hour the hall is live. See also Medium-voltage switchgear, Low-voltage switchboard, Power usage effectiveness
- Low-voltage switchboardLV switchboard
The main distribution board on the low-voltage side of each transformer, holding the air circuit breakers that feed the UPS systems, mechanical plant and house services, and the generator connection point. It is built in separated sections so one can be worked on while others stay live. It concentrates most of a facility's arc flash energy and hosts the generator transfer logic, so commissioning tests it hardest.
Show in diagramHide diagram
The LV switchboard, where the generator connects and the transfer logic acts. See also Transformer, Automatic transfer switch, Arc flash
- Uninterruptible power supplyUPS
A system that holds the IT load on stored energy during the seconds between a mains failure and the generators taking over, and conditions the power it passes through. Static systems use power electronics with batteries; rotary systems use a spinning mass, sometimes coupled to a diesel engine. A double-conversion static UPS loses a few percent of its throughput as heat every hour, so partial-load efficiency and a high-efficiency mode bear directly on operating cost.
Show in diagramHide diagram
The UPS on each path, holding the rack through the seconds between a mains failure and generator start. See also Battery autonomy, Battery chemistry, Standby generator
- Battery autonomy
The time a UPS can carry its rated load from batteries alone, typically five to fifteen minutes for a static system and tens of seconds for a flywheel. It only needs to exceed the generators' start time with margin for a failed first start; longer autonomy buys little beyond a tidy shutdown if the generators fail. Autonomy is quoted at full load and new battery capacity, so a lightly loaded hall with aged batteries behaves differently.
Show in diagramHide diagram
The battery string beneath each UPS. Five to fifteen minutes of autonomy is typical; the generator needs a fraction of that. See also Uninterruptible power supply, Standby generator, Battery chemistry
- Battery chemistry
The cell technology behind a UPS, chiefly valve-regulated lead-acid or lithium-ion, with sodium and nickel-zinc cells appearing. Lead-acid is cheap but heavy, short-lived and temperature-sensitive; lithium-ion is lighter, longer-lived and tolerates more cycles, but costs more, needs a battery management system and falls under fire codes that may require separate rooms, suppression and thermal-runaway testing. The chemistry decides battery room size, replacement cycle and insurance terms, which outweigh purchase price.
See also Uninterruptible power supply, Battery autonomy, Fire detection and suppression
- Standby generator
An engine-driven alternator, usually diesel, that carries the facility when the grid fails. It must start and accept load within the UPS autonomy, and a Tier III or IV facility must rate its generators for continuous full-load operation and hold at least twelve hours of fuel on site at design load. Generators are the largest items in planning terms and emissions limits may restrict testing hours, so gas engines and fuel cells are being trialled.
Show in diagramHide diagram
One generator set per path, rated for continuous operation, with at least twelve hours of fuel at design load. See also Battery autonomy, Automatic transfer switch, Load bank
- Automatic transfer switchATS
A switch that moves a load between two sources, typically from the failed utility to the generators and back, without an operator. Transfer takes seconds and is covered by the UPS. Open transition has a brief break; closed transition parallels the sources briefly so returning to utility causes no second break. In large facilities main switchboard breakers and control logic do the job, and that logic is what integrated systems testing exercises most.
Show in diagramHide diagram
The transfer breaker between generator and LV board. It opens and closes in seconds; the UPS covers the gap. See also Low-voltage switchboard, Standby generator, Integrated systems test
- Static transfer switchSTS
A solid-state switch that moves a load between two independent power sources within a quarter of a cycle, fast enough that equipment downstream does not notice. It gives single-corded equipment two upstream paths, and in block redundant designs it steers a block of load to the reserve system. An STS is itself a single point for the load behind it, so dual-corded equipment is preferred and an STS used only where that is impossible.
Show in diagramHide diagram
Block redundant: four primary systems and one reserve. The STS moves a failed block's load to the reserve within a quarter of a cycle. See also A and B feeds, Distributed redundant and block redundant topologies, Automatic transfer switch
- Power distribution unitPDU
A floor-standing cabinet that splits a UPS output feed into breakered, metered circuits for rows of racks, in some markets through a transformer stepping down to rack voltage. Remote power panels, smaller boards among the racks, bring breakers closer to the equipment. The same term is applied to power strips inside racks, which confuses capacity discussions. Its rating sets the load a row can draw, and in high-density halls the circuit count runs out first.
Show in diagramHide diagram
PDU and busway on each path, the last stage before the rack. See also Busway, Uninterruptible power supply, Stranded capacity
- Busway
An overhead track of enclosed conductors running along a row of racks, from which tap-off boxes draw power at any point. It replaces fixed PDU-to-rack cabling with circuits that can be added, moved or re-rated by fitting a different tap-off, without shutting the row down. It is now standard in slab halls because it keeps the floor clear for liquid pipework and a single run can match a row of accelerator racks.
Show in diagramHide diagram
The overhead busway with its three tap-off boxes. Circuits are added by fitting a tap-off, without shutting the row down. See also Power distribution unit, Raised floor and slab, Design density
- Redundancy topologyN, N+1, 2N, 2N+1
The notation for how many spare units a system has beyond the number, N, needed to carry the load. N+1 adds one spare on a shared path, 2N duplicates the whole system and its path, and 2N+1 adds a spare to each duplicate. The notation describes components, so a facility can be 2N in UPS yet N+1 in chillers. A claim should say which system the letters refer to and whether the paths are physically separated.
Show in diagramHide diagram
N+1: three units installed for a load that needs two. One can fail or be serviced; the shared bus cannot. See also Distributed redundant and block redundant topologies, A and B feeds, Tier classification
- Distributed redundant and block redundant topologies
Two ways of achieving redundancy with less equipment than full duplication. In a distributed redundant design, three or more systems share the load so any one can fail and the others absorb it. In a block redundant design, several primary systems share one reserve, reached through static transfer switches when a primary fails. Both give near 2N resilience for less capital, at the price of maintaining the load mapping as tenants come and go.
Show in diagramHide diagram
Distributed redundant: three systems each loaded to two thirds. Any one can fail and the other two carry the full load. See also Redundancy topology, Static transfer switch, Capacity planning
- A and B feeds
Two independent power paths to each rack, each from its own UPS and distribution, so a dual-corded server keeps running when either is lost. Each path carries half the load and must be sized for all of it, so resilience depends on keeping neither path above fifty percent. Accelerator servers with several power supplies complicate this, since they may run on the remaining supplies with less margin than specified, which should be tested before loading a hall.
Show in diagramHide diagram
The two paths from intake to rack, meeting only at the dual-corded server. See also Redundancy topology, Static transfer switch, Fault tolerance
- Load bank
A bank of resistive and reactive elements that draws a controlled electrical load so generators, UPS systems and distribution can be tested at full rating before any IT equipment is installed. They are used at every commissioning level and in annual generator tests. A facility never load-tested at full capacity has never been proven at it, and generators that only run lightly loaded accumulate deposits that reduce reliability.
See also Commissioning levels, Integrated systems test, Standby generator
- Arc flash
The explosive release of energy when an electrical fault arcs through air, producing heat, pressure and molten metal that can kill anyone nearby. IEEE 1584 incident energy calculations for each switchgear item set protective equipment, approach distances and live work practices. It governs how a power train can be maintained live, so arc-energy-reducing switchgear, remote racking and arc-resistant construction protect staff and decide which maintenance needs a shutdown.
See also Low-voltage switchboard, Medium-voltage switchgear, Maintenance regime
- Power quality
How closely the voltage delivered to equipment keeps the sinusoidal shape, magnitude and frequency it was designed for. Harmonics from power electronics, voltage sags from grid faults and switching transients all count as poor quality, and a UPS exists partly to correct them. Accelerator clusters are themselves a power quality problem: thousands of synchronised power supplies stepping together produce current swings and harmonics that the transformers, generators and grid connection must absorb.
See also Uninterruptible power supply, Accelerator load step, Transformer
- Stranded capacity
Power a facility has paid for and cannot sell, because another limit, cooling, floor space, structural load, circuit positions or a tenant's contracted but unused allocation, is reached first. A low-density hall with a large power allocation strands megawatts behind its cooling limit; a tenant that contracts 5 MW and draws 2 MW strands 3 MW behind its contract. A facility's real value is how much connected power it can deliver and bill.
Show in diagramHide diagram
The hatched band between what the power train can supply and what can actually be sold, lost to cooling, floor loading or circuit positions. See also Oversubscription, Capacity planning, Design density
- Oversubscription
Contracting more IT capacity to tenants than the power train can deliver at once, relying on tenants rarely drawing their full allocation together. The assumption holds for mixed enterprise workloads. It fails for accelerator clusters, which run near full draw for days during training, so a facility hosting AI tenants must size its power train to the sum of their allocations, and an operator carrying enterprise assumptions has less saleable capacity than its plans show.
Show in diagramHide diagram
The dashed outline: contracted capacity wider than the deliverable bar. Accelerator tenants draw to the edge of their contracts and expose it. See also Stranded capacity, Accelerator load step, Take-or-pay
- Accelerator load step
The rapid change in facility power when a synchronised training cluster starts, pauses or checkpoints and thousands of accelerators move between idle and full draw within a fraction of a second. The UPS, the generators on standby power and the grid connection all see the step, and none were designed for a load that behaves as one machine. Operators specify UPS and generator step response; schedulers smooth the ramp or keep accelerators busy in pauses.
See also Power quality, Oversubscription, Uninterruptible power supply
Group 03
Cooling and environment
Every watt delivered to a rack must be removed again, and the cooling plant is where a facility's second largest capital cost, most of its water use and most of its energy overhead sit. The shift of AI hardware to liquid cooling changes the plant, the hall and the temperatures a facility runs at, and a design that has not made that shift cannot host current accelerator racks.
- Sensible and latent heat
Two forms of heat a cooling system removes. Sensible heat changes air temperature and is what IT equipment produces; latent heat is released when water condenses or evaporates, as when a coil runs cold enough to dehumidify. A data centre load is almost entirely sensible, so a well-designed plant runs its coils above the dew point and removes no moisture, since latent cooling spends energy on humidity that must be put back.
See also Humidity and contamination control, CRAC and CRAH units, Supply and return temperatures
- CRAC and CRAH units
Computer room air conditioners and computer room air handlers, the units that move air through a hall. A CRAC contains its own refrigeration circuit and rejects heat to an outdoor condenser; a CRAH is a fan and a chilled-water coil served by central chillers. CRAHs scale better and are the norm in large facilities. Either way the fans are the air-side energy cost, so containment and higher supply temperatures, which let fans slow, matter greatly to PUE.
Show in diagramHide diagram
The CRAH on the air path, a fan and a chilled-water coil fed from the same facility water loop. See also Chilled water system, Hot aisle and cold aisle containment, Power usage effectiveness
- Chilled water system
A central arrangement in which chillers cool water that is pumped through the building to air handlers and coolant distribution units, returning warm to be cooled again. It separates heat rejection from the hall, allows redundancy at the plant level and carries far more heat per pipe than air does per duct. Chilled water temperature is a design choice trending upward, because warmer water allows more free cooling hours and is all that liquid-cooled racks require.
Show in diagramHide diagram
The facility water loop from CDU and CRAH to the chillers. See also Chiller, Free cooling and economisers, Facility water and technology cooling loops
- Chiller
A refrigeration machine that removes heat from the chilled water loop and rejects it outdoors, through fans if air-cooled or a condenser water loop and cooling tower if water-cooled. Water-cooled chillers are more efficient and use water; air-cooled chillers use no water and more electricity, and lose capacity on the hottest days, when the grid is stressed. A facility claiming low water use has usually chosen air-cooled plant and should be asked about summer energy.
Show in diagramHide diagram
The chiller between the facility water loop and the condenser loop. The dashed bypass shows the hours it is not needed. See also Chilled water system, Cooling tower, Water usage effectiveness
- Free cooling and economisers
Cooling with outdoor air or water whenever conditions allow, instead of the chillers. An air-side economiser brings filtered outdoor air into the hall; a water-side economiser uses cooling towers or dry coolers to chill the water loop directly. Hours a year depend on climate and the supply temperature the hall tolerates; a few degrees more can add hundreds. Liquid cooling at warm water temperatures extends it to almost all year in most climates.
Show in diagramHide diagram
The dashed economiser bypass around the chiller. Warmer facility water keeps it open for more hours of the year. See also Supply and return temperatures, Adiabatic cooling, Chiller
- Adiabatic cooling
Cooling by evaporating water into an air stream, lowering its temperature toward the wet-bulb temperature at the cost of adding moisture. Sprays or wetted pads on dry coolers and air handlers extend free cooling into warmer weather for a fraction of a chiller's energy. Water is the trade: an adiabatic system can be a site's largest water consumer in summer, and its low-energy claims should be read alongside its water usage effectiveness and supply reliability.
Show in diagramHide diagram
Adiabatic pads on the dry cooler extend the bypass into warmer weather, at the cost of water. See also Free cooling and economisers, Water usage effectiveness, Cooling tower
- Cooling tower
A structure that rejects heat from a water loop by evaporating part of the water, used with water-cooled chillers or directly as a water-side economiser. Towers are the most energy-efficient heat rejection available; their price is water consumption, treatment to control scale and bacteria, and a plume on cold mornings that planning authorities notice. Where water is constrained, dry or hybrid coolers that evaporate only at peak replace them, costing fan energy and higher loop temperatures.
Show in diagramHide diagram
The heat rejection yard along the north wall. Towers, dry coolers or air-cooled chillers sit here, and the choice sets the site's water use. See also Chiller, Water usage effectiveness, Planning and permitting
- ASHRAE thermal envelope
The inlet temperature and humidity ranges ASHRAE publishes for IT hardware. The recommended envelope is 18 to 27 degrees Celsius at the server inlet, with wider allowable classes and a narrower class for the densest air-cooled hardware. Colocation temperature clauses cite it, and it applies at the inlet, so 27 degrees in the cold aisle and 40 in the hot aisle complies in full. Separate classes cover facility water for liquid-cooled equipment.
See also Supply and return temperatures, Service level agreement, Humidity and contamination control
- Supply and return temperatures
The temperature at which cooling air or water reaches IT equipment and at which it returns. Raising supply temperature is the cheapest efficiency gain, since every degree eases the chillers and extends free cooling; the limit is the inlet envelope and the margin wanted for a cooling failure. Liquid cooling moves supply from the low twenties for air to the thirties and forties for water, which lets a facility run most of the year without chillers.
Show in diagramHide diagram
Four temperature tags: TCS supply in the thirties or forties, facility water a few degrees below it, cold aisle inside the 18 to 27 degree envelope, hot aisle above it. See also ASHRAE thermal envelope, Delta T, Free cooling and economisers
- Delta TΔT
The temperature rise across equipment or a loop, from supply to return. A high delta T means each litre of water or cubic metre of air carries more heat, so pumps and fans move less and the plant can be smaller. IT equipment sets the air-side delta T through its fan speeds, and air mixing in a poorly contained hall collapses it, so return temperature at the cooling unit measures how well a hall is managed.
Show in diagramHide diagram
Delta T is the difference between each supply tag and its return. A larger difference means less water or air moved for the same heat. See also Supply and return temperatures, Hot aisle and cold aisle containment, Coolant distribution unit
- Liquid cooling
Removing heat from IT equipment with a liquid rather than air, at the chip, the rack door or by immersion. Water carries heat several thousand times better than air by volume, making racks above a few tens of kilowatts practical. It is the default for accelerator racks and changes the facility: pipework and CDUs enter the hall, leak detection and water quality become disciplines, and the air-side plant shrinks but stays for the heat still leaving through air.
Show in diagramHide diagram
The liquid path from cold plate to CDU. Water carries heat several thousand times better than air by volume. See also Direct-to-chip cooling, Coolant distribution unit, Design density
- Direct-to-chip cooling
Liquid cooling in which cold plates sit directly on the processors and memory, with coolant piped to each server through quick-disconnect couplings and rack manifolds. It captures most of a server's heat; the remainder, from power supplies and drives, is still rejected to air. Current accelerator systems are built for it, and facility water in the thirties and forties suffices, since the coolant only needs to be cooler than the chip.
Show in diagramHide diagram
Cold plates on the processors, fed through the rack manifold. The coolant needs only to be cooler than the chip surface. See also Liquid cooling, Rear-door heat exchanger, Facility water and technology cooling loops
- Rear-door heat exchangerRDHx
A water-cooled coil in place of a rack's rear door, through which server exhaust passes before entering the hall, driven by server fans or fans in the door. It removes heat at the rack without touching the servers, allowing racks of several tens of kilowatts where the air-side plant could not otherwise cope. Rear doors are the usual way to retrofit density into an air-cooled hall and to handle the residual air-side heat of direct-to-chip racks.
Show in diagramHide diagram
The rear-door coil on the rack, taking the residual air-side heat before it reaches the hall. See also Direct-to-chip cooling, Liquid cooling, CRAC and CRAH units
- Immersion cooling
Submerging whole servers in a tank of dielectric fluid that carries heat away from every component. Single-phase systems pump the warm fluid to a heat exchanger; two-phase systems let it boil on hot components and condense on a coil above. Immersion removes fans, dust and hot spots and tolerates high density, but needs hardware built for it, changes servicing and, for two-phase fluids, faces regulatory pressure on fluorinated chemicals. It remains a minority method beside direct-to-chip for accelerators.
See also Liquid cooling, Direct-to-chip cooling, Remote hands
- Coolant distribution unitCDU
A unit of heat exchanger, pumps, filters and controls separating the facility water loop from the clean loop to the cold plates and regulating flow and temperature to the racks. CDUs sit in the row or rack, rated from tens of kilowatts to over a megawatt. It is where facility responsibility meets the tenant's and a new single point of failure, so its redundancy, leak detection and water quality belong in the design review and the SLA.
Show in diagramHide diagram
The CDU: heat exchanger, pump and filter between the two loops, and the boundary between tenant and landlord water. See also Facility water and technology cooling loops, Direct-to-chip cooling, Service level agreement
- Facility water and technology cooling loopsFWS and TCS
The two water circuits in a liquid-cooled facility. The facility water system is treated building water carrying heat from the coolant distribution units to the chillers or dry coolers; the technology cooling system is the closed, clean loop between the CDU and the cold plates, with controlled chemistry, filtration and materials. Separation protects the servers from building water and confines any failure, and the CDU interface is the natural landlord and tenant boundary.
Show in diagramHide diagram
The facility water loop on the building side of the CDU and the technology cooling loop on the rack side. They never mix. See also Coolant distribution unit, Chilled water system, Direct-to-chip cooling
- Water usage effectivenessWUE
A metric for water consumption, litres of water per kilowatt-hour of IT energy, standardised in the ISO/IEC 30134 series. Site WUE counts water used on the premises, mainly for evaporative cooling and humidification; source WUE adds water consumed generating the facility's electricity, which can be larger. A low site WUE is easy with air-cooled plant at the cost of energy, so WUE and PUE should be read together; quoting one alone hides the trade-off.
See also Power usage effectiveness, Cooling tower, Adiabatic cooling
- Power usage effectivenessPUE
The ratio of total facility energy to IT equipment energy over a year, standardised in ISO/IEC 30134-2, where 1.0 means no overhead from cooling, losses or lighting. It hides where IT energy is measured, since a UPS output figure counts distribution losses as IT; it counts fans and pumps inside racks and CDUs as IT; and it ignores whether the IT does useful work. A partial PUE for one subsystem or hall is sometimes quoted as the whole.
Show in diagramHide diagram
PUE is the facility bar divided by the IT bar. A figure of 1.2 means the overhead band is one fifth the width of the IT bar. See also IT load, Facility load, Water usage effectiveness
- Heat reuse
Capturing the heat a facility rejects and supplying it to district heating, a greenhouse or an industrial process nearby. Air-cooled halls reject heat too cool to be worth much without heat pumps; liquid cooling delivers water in the forties, which heat pumps lift cheaply. Reuse needs a year-round heat customer within pipe distance, and some jurisdictions now require new facilities above a size threshold to assess it, so it belongs in the planning case.
Show in diagramHide diagram
The heat reuse branch off the facility water return, carrying water warm enough for a heat pump to lift to heating temperature. See also Supply and return temperatures, Liquid cooling, Planning and permitting
- Fire detection and suppression
Systems that detect a fire early and extinguish it without destroying equipment. Aspirating smoke detection samples hall air and alarms far below a conventional detector's threshold. Suppression is a clean agent, an inert gas or chemical that floods the room without residue, or pre-action sprinklers, whose pipes stay dry until both a detector and a head trigger, so one damaged head cannot flood a hall. Both are usually fitted, gas first and water as last resort.
See also Battery chemistry, Fault tolerance, Building management system
- Humidity and contamination control
Keeping hall air within the humidity band and the particulate and gas limits electronics need. Low humidity risks electrostatic discharge, high humidity condensation and corrosion, and ASHRAE specifies the band as a dew point range with a relative humidity ceiling. Filtration to the relevant ISO 14644 class controls particulates, and gaseous contaminants, such as sulphur compounds near industry or the coast, are assessed on the ISA severity scale. Air-side free cooling makes all three harder.
See also ASHRAE thermal envelope, Sensible and latent heat, Free cooling and economisers
Group 04
Operations and commercial
Capital earns nothing until a hall passes its tests and a tenant starts paying, and it keeps earning only while the service agreement is met. These terms describe the milestones that release revenue, the measurements that prove the service, and the contract structures that decide how much of a facility's capacity turns into cash and when.
- Commissioning levelsL1 to L5
Staged testing that proves a facility works as designed before it carries IT load, numbered one to five. Level 1 is the factory witness test, level 2 inspection on delivery, level 3 start-up and verification of each item, level 4 functional testing of each system, and level 5 the integrated systems test of the whole building. Each has scripts, witnesses and sign-offs, and compressing them to meet a date is the commonest cause of early-life outages.
Show in diagramHide diagram
Levels 1 to 4: factory test, delivery inspection, start-up, and functional testing of each system in turn. See also Integrated systems test, Load bank, Practical completion and ready for service
- Integrated systems testIST
The final commissioning stage, in which the whole facility runs at design load on load banks while failures are induced: utility cut, generators started, UPS discharged, chillers tripped and transfers exercised, with hall temperature watched throughout. It is the only point at which electrical and mechanical systems are proven together, and where control logic faults appear. A tenant or its adviser should witness it, and hall acceptance is usually conditional on the results.
Show in diagramHide diagram
Level 5, the integrated systems test, the only stage at which every system is proven together under full load. See also Commissioning levels, Load bank, Automatic transfer switch
- Practical completion and ready for servicePC and RFS
Two milestones often confused. Practical completion is the construction contract's term for the builder finishing, bar minor defects, and handing the building to the owner. Ready for service is the lease's term for a commissioned hall where the tenant can install and rent starts. The gap, holding commissioning, certification and fit-out, can run to months, and who bears a slip's cost is among the most negotiated points in a lease.
Show in diagramHide diagram
Practical completion, where the builder hands over, and ready for service, where the rent starts. The gap between the two ticks holds commissioning, certification and fit-out. See also Commissioning levels, Ramp schedule, Take-or-pay
- Building management systemBMS
The control system that runs a facility's mechanical plant: chillers, pumps, air handlers, valves and dampers, with the electrical side usually monitored by a separate power monitoring system. It executes the sequences of operation that commissioning tested, including the response to a cooling failure, and holds the trend data. It is most often implicated when an outage is traced to a control fault, so its software changes deserve the same change control as the plant.
See also Data centre infrastructure management, Integrated systems test, Chilled water system
- Data centre infrastructure managementDCIM
Software that records what is installed where, how much power, cooling, space and weight each position uses and has left, and how those figures change over time. Where the BMS controls plant, DCIM manages capacity and sources the utilisation reports an operator gives tenants and financiers. Its value depends on keeping it current, and a facility whose DCIM disagrees with the floor has no reliable view of its stranded capacity.
See also Building management system, Capacity planning, Stranded capacity
- Service level agreementSLA
The schedule in a colocation contract stating what the operator guarantees, typically power availability at the rack, inlet temperature and humidity within a stated envelope, remote hands response times, and the credits paid when one is missed. Credits are capped, usually at a fraction of a month's fees, so an SLA defines the service without compensating for its loss. The measurement points, exclusions for planned maintenance and definition of an outage decide what the headline figure means.
See also Availability nines, ASHRAE thermal envelope, Remote hands
- Availability nines
Stating availability as a percentage of time in service, where 99.9 percent allows about 8.8 hours of outage a year, 99.99 percent about 53 minutes and 99.999 percent about 5 minutes. The figure says nothing about distribution, and one five-hour event in a training run costs far more than sixty five-minute events over a decade. Nines follow the SLA's own definitions, so a facility can report full availability through an event a tenant saw as an outage.
See also Service level agreement, MTBF and MTTR, Tier classification
- Maintenance regime
The planned programme of inspection, servicing and replacement for a facility's plant: generator runs and load tests, UPS battery checks, switchgear inspection and thermography, chiller servicing, filter changes and water treatment. Preventive regimes work to fixed intervals; condition-based ones use sensor data to service equipment when needed. The regime is what concurrent maintainability exists to allow, and the fraction completed on time is a better leading indicator of reliability than outage history.
See also Concurrent maintainability, MTBF and MTTR, Load bank
- MTBF and MTTR
Mean time between failures and mean time to repair, which together give availability, since availability equals MTBF divided by the sum of the two. Redundancy makes a single failure harmless, lengthening the system's effective MTBF without changing that of its parts. Operations decide MTTR through spares on site, staff on shift and vendor response times, and a long MTTR on a critical component leaves a redundant design exposed for the whole repair.
See also Availability nines, Maintenance regime, Redundancy topology
- Capacity planning
Continuously matching the power, cooling, space, structural load and circuit positions a facility has to the demand its tenants have contracted and will draw. It runs on DCIM data and tenants' ramp forecasts, and its product is how much saleable capacity remains and when it runs out. Accelerator tenants make it harder in one way and easier in another: their draw stays close to contracted load but changes in large steps with each hardware generation.
Show in diagramHide diagram
The contracted bar against the design bar. Capacity planning is the work of keeping the gap between them small and known. See also Data centre infrastructure management, Stranded capacity, Ramp schedule
- Retail colocation
Colocation sold by the rack or kilowatt in a shared hall, on terms of one to a few years, with the operator providing power, cooling, security and remote hands. Retail is priced per kilowatt per month, with higher unit prices and operating cost than wholesale because of tenant numbers, churn and services. It is the segment least suited to AI hardware, since a shared air-cooled hall cannot supply the density, though operators increasingly offer liquid-ready zones for inference.
See also Wholesale and hyperscale colocation, Pricing units, Remote hands
- Wholesale and hyperscale colocation
Capacity sold in megawatt blocks, usually whole halls or buildings, on terms of five to fifteen years to a few large tenants. Wholesale tenants take a turnkey hall and operate their own IT; hyperscale tenants may take a powered shell or build-to-suit with their own fit-out standards. Unit prices are lower than retail and the operating burden lighter; financiers underwrite the lease's credit quality and length, so the facility behaves more like real estate than a service business.
See also Retail colocation, Powered shell, Take-or-pay
- Pricing unitsper kW, per MW, per rack
The basis on which capacity is charged: per rack in retail, per kilowatt of contracted IT load in most colocation and per megawatt in wholesale, usually per month. Electricity is bundled into the rate or passed through at metered cost plus overhead, and the two give different exposures to power prices and PUE. Offers compare only on the same basis, since a low bundled rate at a poor PUE can cost more than a higher metered rate.
See also IT load, Power usage effectiveness, Take-or-pay
- Take-or-pay
A contract term under which the tenant pays for its full contracted capacity whether or not it uses it. It transfers utilisation risk from operator to tenant and makes a lease financeable, since revenue does not depend on the tenant's ramp. For the tenant it is the cost of reserving capacity in a tight market, and stranded capacity sits on its ledger. Most wholesale and hyperscale leases are take-or-pay after an agreed ramp.
Show in diagramHide diagram
The flat line after the ramp: full payment for contracted capacity whether or not it is drawn. See also Ramp schedule, Stranded capacity, Wholesale and hyperscale colocation
- Ramp schedule
The timetable over which a tenant's contracted capacity and payments step up from lease start to full commitment. A ramp gives the tenant time to install hardware and the operator time to phase fit-out, and typically runs months to a year or two. AI tenants compress ramps because hardware arrives in clusters and draws power within weeks, good for revenue and hard on commissioning, since full load arrives before the hall has run at anything less.
Show in diagramHide diagram
The stepped ramp from first payment to full commitment. AI tenants compress it to weeks. See also Take-or-pay, Practical completion and ready for service, Capacity planning
- Fibre entry
The points where telecommunications cables enter the building, from boundary ducts through an entrance room to the meet-me room. A resilient facility has at least two entries on separate sides, fed by separate duct routes, so one excavation cannot cut both. Entries are part of the shell and hard to add later, and their number and separation decide how much route diversity a tenant can buy, whatever the Connectivity layer offers outside the fence.
Show in diagramHide diagram
Two duct routes from the fence, entering on opposite sides of the building. One excavation cannot cut both. See also Meet-me room, Cross-connect, TIA-942
- Meet-me roomMMR
A secured room where carriers terminate their cables and tenants connect to them, with cross-connects on patch panels under the operator's control. A facility with two meet-me rooms on separate entries can offer genuinely diverse connections; one with a single room cannot, whatever its carrier count. The MMR is the boundary between the Data Centre and Connectivity layers, and an operator that charges for cross-connects earns a recurring fee from every connection made in it.
Show in diagramHide diagram
MMR A and MMR B at opposite ends of the building, each on its own entry. See also Fibre entry, Cross-connect, Physical security layers
- Cross-connect
A physical cable, usually fibre, run by the operator between two parties' equipment, most often a tenant and a carrier in the meet-me room. It is ordered as a service, installed in days and billed monthly while it stays in place. Fees are small individually and large in aggregate, and their pricing, and whether a tenant may run its own, affects every later connection. What the cross-connect reaches belongs to the Connectivity layer.
See also Meet-me room, Fibre entry, Remote hands
- Remote hands
A service in which operator technicians perform physical tasks on a tenant's equipment: power cycling, swapping drives or cables, racking replacements. It is sold by the hour or included up to a limit, with response times set in the SLA. It lets a tenant run hardware in a facility it never visits; for an accelerator fleet, where a failed component idles a training job, response time and competence with liquid-cooled hardware matter more than the hourly rate.
See also Service level agreement, Retail colocation, Liquid cooling
- Physical security layers
The concentric controls between the public road and a tenant's equipment: perimeter fencing and vehicle barriers, a gatehouse, building access with identity checks, mantraps into the halls, caged or locked cabinets, and cameras and logs throughout. Vendors label these as security tiers or layers, with no common standard behind the numbers. Audit evidence matters, since the certifications a tenant relies on test whether controls are operated as described, and tenants' own compliance obligations often require inspection.
Show in diagramHide diagram
Fence, vehicle barrier and gatehouse, the outer layers of security before the building's own. See also Certifications, Meet-me room, Data hall
- CertificationsISO 27001, SOC 2, PCI DSS
Third-party attestations that a facility's controls meet a published standard. ISO 27001 certifies an information security management system; SOC 2 is an auditor's report, with no certificate, on controls against trust services criteria over a period for Type II; PCI DSS covers payment card data and, for a colocation operator, only its physical and environmental controls. None covers resilience or uptime, the concern of the Tier and TIA-942 schemes, and each is only as broad as its scope statement.
See also Physical security layers, Tier classification, TIA-942
- Decommissioning and refresh
Removing a tenant's hardware at the end of its life or lease and installing its replacement. IT hardware is refreshed every three to five years, accelerators faster, against a facility life of fifteen to twenty-five years, so a hall sees several generations, each denser and heavier. It involves certified data destruction, asset disposal and making good; the refresh is when a facility learns whether its density, floor loading and cooling carry the next generation.
See also Design density, Structural loading, Build-to-suit
Where this leads
What Outpace does with this vocabulary.
The terms of each layer describe the gap between what an asset could do and what it does. Outpace underwrites that gap. The thesis sets out why contracted, productive output matters more than installed capacity.