Power glossary
The vocabulary of the Power layer.
Plain definitions of the terms that appear in connection offers, network studies, power purchase agreements and energy invoices, written for the people who finance and operate the facilities that depend on them.
The terms are in four groups, from the grid a facility connects to, through the generation and contracts that supply it, to the electrical plant that delivers it to the fence and the economics and provenance that decide what it costs and what can be said about it. Each definition is written for owners, operators and investors who need to read a connection study, a supply contract or an energy invoice with a critical eye. Where a term bears directly on the economics of an AI facility, the definition says how.
Groups follow the electricity. Grid and connection describes the network and the right to draw from it, generation and procurement describes where the energy comes from and how it is bought, electrical plant to the fence describes the equipment between the network and the facility boundary, and economics and provenance describes what the energy costs and what can be claimed about its origin. Where terminology differs between the Australian National Electricity Market and other markets, the definition says so.
Part of the Power layer. All glossaries
Group 01
Grid and connection
A connection is the longest lead item in most AI facility programmes and the one the owner controls least. The size, firmness and timing of the right to draw power decide when a site can earn, and the physical condition of the network around it decides how often it is interrupted.
- Transmission network
The high-voltage part of the grid that carries bulk power from generators to load centres, at 132 kV and above in most Australian networks and at comparable voltages elsewhere. Transmission lines are few, long and heavily loaded, and connecting to one gives access to the largest blocks of capacity. In the National Electricity Market each region's transmission assets belong to a transmission network service provider, and a load of data centre scale usually connects here.
Show in diagramHide diagram
The transmission span. At 132 kV and above in most Australian networks, this is where a load of data centre scale connects. See also Distribution network, Point of connection, Network capacity
- Distribution network
The medium and low-voltage part of the grid between transmission substations and end users, at up to 66 kV in most Australian networks and below about 100 kV elsewhere. It holds little spare capacity at any one point; a facility of a few tens of megawatts may connect here, but above that reinforcement usually costs more than a transmission connection. Owners are distribution network service providers in Australia and utilities or distribution system operators elsewhere.
Show in diagramHide diagram
The distribution span, at 66 kV and below in most Australian networks. Capacity at any one point is a few tens of megawatts. See also Transmission network, Hosting capacity, Network augmentation
- Point of connection
The physical and contractual boundary where the facility's installation meets the network, usually a set of terminals in a substation or on an incoming line. Ownership, maintenance, metering and the performance standards the connecting party must meet are all defined here. In Outpace's value chain it is also the boundary between the Power layer and the Data Centre layer: upstream is access and supply, downstream is the facility.
Show in diagramHide diagram
The point of connection. Ownership, metering and performance standards change hands at this dot, and so does the layer. See also Connection offer and agreement, Metering and settlement, Substation
- Connection enquiry and application
The formal process by which a prospective load asks a network owner for a connection and learns what it takes. In the National Electricity Market the sequence is enquiry, application, offer and agreement under Chapter 5 of the National Electricity Rules, with system studies between steps; other grids have equivalents such as the interconnection request. Here a site's claimed capacity first meets the network's real condition; most sites marketed as having power have not passed this stage.
Show in diagramHide diagram
The enquiry is the first of the four steps under Chapter 5 of the National Electricity Rules. A site with power has completed all four. See also Connection offer and agreement, Interconnection queue, Network capacity
- Connection offer and agreement
The contract between the connecting party and the network owner that sets the capacity, voltage, performance standards, charges and timing of a connection. An offer precedes it and may be conditional on augmentation works, further studies or payments. A signed agreement with a defined capacity and energisation date is the only document that turns a claim of available power into a right; letters of intent, enquiry responses and capacity maps do not.
Show in diagramHide diagram
The agreement, the fifth box. Everything before it is an estimate; everything after it is a programme. See also Connection enquiry and application, Performance standards, Energisation
- Interconnection queue
The ordered list of projects waiting for a network owner or system operator to study and approve their connection. Each connection changes the flows and fault levels later ones are studied against, so studies run in sequence. In several large markets the generation queue now outlasts the construction time of the plant behind it, and large loads have joined the same bottleneck. Queue position is an asset, and in some jurisdictions a transferable one.
Show in diagramHide diagram
Studies run in sequence because each connection changes the case the next is studied against. The queue is the wait to enter this box. See also Connection enquiry and application, Network capacity, Network augmentation
- Network capacity
The additional load a point on the network can supply without breaching thermal, voltage or stability limits under the operator's planning criteria. It depends on the lines, transformers and generation behind the point and on what other users already draw. Capacity is quoted for a point and a time rather than for a parcel of land; a figure without a point of connection and a planning case attached is a marketing number.
See also Hosting capacity, Firm and non-firm access, Network augmentation
- Firm and non-firm access
A firm connection has its full capacity available under normal and credible contingency conditions; a non-firm one may be reduced when the network is constrained. Non-firm or flexible connections come sooner and cheaper because the network is not reinforced for the worst hour. The questions for an AI facility are how many hours a year the reduction bites and whether the workload tolerates them. Calling a non-firm connection firm is the most common misstatement in site marketing.
See also Curtailment, Network capacity, Demand response
- Curtailment
A reduction in the power a connected party may inject or draw, instructed by the network owner or system operator to keep the network within limits. For generators it means spilling energy; for loads, reducing demand on instruction. Curtailment terms sit in the connection agreement and any flexible connection arrangement, and the expected hours and megawatts of curtailment are an input to the facility's revenue model.
See also Firm and non-firm access, Load shedding, Demand response
- Hosting capacity
The generation or load a section of the distribution network can accept without upgrades, as published by the network owner in capacity maps and planning reports. These figures are screening tools: they reflect a standard planning case, are updated infrequently and rarely count applications already in progress, so they can overstate what remains available. They are useful for ruling sites out and poor evidence for ruling them in.
See also Network capacity, Connection enquiry and application, Distribution network
- Network augmentation
Works that increase the existing network's capacity to accommodate a new connection: a new transformer, a reconductored line, an additional substation bay or a second circuit. Who pays depends on the regulatory regime; in Australia the connecting party typically funds augmentation that serves only it, while shared network upgrades pass through the regulated planning process and asset base. Its lead time, set by transformer and switchgear supply, is usually the critical path of a large connection.
Show in diagramHide diagram
Augmentation works on the shared network, carried out by the network owner after the agreement and usually the critical path. See also Contestable works, Transformer lead time, Connection offer and agreement
- Contestable works
Connection works the connecting party may procure from a competing contractor rather than from the incumbent network owner. In the National Electricity Market dedicated connection assets such as a new substation or spur line are generally contestable while shared network works are not; the split differs by state and again in other countries. Contestability gives the connecting party control of price and programme for assets it will own, instead of waiting on the incumbent's workload.
Show in diagramHide diagram
The split within the works box. Dedicated connection assets can be built by a contractor of the connecting party's choice; shared network works cannot. See also Network augmentation, Connection assets, Substation
- System strength
The ability of the network at a point to hold a stable voltage waveform through a disturbance, measured by the fault current available there. Strength comes mainly from synchronous machines, so a network with many inverters and few spinning machines is weak. Weak networks impose tighter performance requirements on new connections and may need synchronous condensers or grid-forming equipment; in the National Electricity Market a party whose equipment reduces system strength can be charged for the remedy.
See also Inertia, Fault level, Grid-forming inverter
- Inertia
The resistance of the power system to changes in frequency, supplied by the rotating mass of synchronous generators and motors. When supply and demand diverge, inertia slows the frequency change and gives control systems time to act. As coal and gas units retire, operators procure inertia directly or substitute fast frequency response from batteries; a facility load or battery that responds within a fraction of a second holds something the operator values.
See also Frequency and voltage, System strength, Grid-forming inverter
- Frequency and voltage
The two quantities a power system is operated to hold within bands: frequency, 50 Hz in Australia and most of the world and 60 Hz in North America and parts of Asia, and voltage at each node within a percentage of nominal. Frequency reflects the supply and demand balance across the whole system; voltage is local and follows reactive power flows. The connection agreement sets what the facility must ride through and must not cause.
See also Inertia, Reactive power, Ancillary services
- Ancillary services
Services the system operator buys to keep frequency, voltage and system security within limits, separately from energy. In the National Electricity Market the main ones are frequency control ancillary services, procured in raise and lower markets from very fast to slow; other systems speak of frequency response, operating reserve and regulation. Large loads with controllable demand or batteries can be paid to provide them, offsetting part of the resilience they would build anyway.
See also Frequency and voltage, Demand response, Battery energy storage system
- Performance standards
The technical requirements a connecting party agrees to meet at the point of connection: voltage and frequency ride-through, reactive capability, harmonic limits, protection settings and behaviour during disturbances. In the National Electricity Market they are negotiated between automatic and minimum access standards and written into the connection agreement; other grids use a grid code. A large AI load built on fast-switching power electronics is studied against them much as a generator is, and that takes months.
Show in diagramHide diagram
Performance standards are negotiated during the studies and fixed in the agreement. The loop-back is a failed study. See also Connection offer and agreement, Power quality, Harmonics
- Network protection
The relays, circuit breakers and communications that detect a network fault and disconnect the smallest possible section within a fraction of a second. A fault on one feeder should not take down the substation, and a fault at the facility should not take down the network. The connection agreement requires the facility's protection to coordinate with the network's, and the grading studies that prove it are part of the connection process.
Show in diagramHide diagram
The protection scheme as the network sees it: relays at the facility must coordinate with those upstream so that a fault here stays here. See also Protection relay, Switchgear, Fault level
- N-1
The planning criterion that a network must keep supplying its load after losing any single element: one line, transformer or generator. A connection meeting N-1 has at least two independent paths, each able to carry the full load. Most transmission networks are planned to N-1 and some critical sections to N-2. A single-circuit spur offers no such redundancy, leaving the facility's own dual feeds, storage and generation to carry the burden.
See also Dual feeds, Firm and non-firm access, Network protection
- Black start
The capability to restore a power system from complete shutdown, using generators that start without external supply and energise the network in stages. System operators contract black start services from specific plants in each region. For a facility the question is where it sits in the restoration sequence: large loads are reconnected late, so on-site generation and storage sized for a short outage may face a long one after a system-wide event.
See also Load shedding, Behind-the-meter and front-of-meter, Inertia
- Load shedding
The deliberate disconnection of load, by automatic relays or the system operator, to prevent collapse when supply falls short. Under-frequency load shedding acts within fractions of a second in predefined blocks; manual shedding follows when reserves are exhausted. Large industrial loads are often in the early blocks because one feeder removes a lot of demand. The connection agreement sets which schemes a facility is in, and exclusion is usually bought with controllable demand.
See also Curtailment, Demand response, Frequency and voltage
- Behind-the-meter and front-of-meter
Where a generator or battery sits relative to the facility's revenue meter. Behind-the-meter assets supply the facility directly; front-of-meter assets sell into the network and the facility buys by contract. Behind-the-meter supply avoids network charges on displaced energy and can ride through a grid outage, but the facility carries the plant's availability, fuel and emissions obligations. As connection timetables lengthen, on-site plant is increasingly proposed as primary supply, turning a few hours a year of standby into continuous duty.
Show in diagramHide diagram
Behind the meter: generation and storage on the facility's side of the point of connection, feeding the site without crossing the network. See also Co-location with generation, Gas peaking plant, Network charges
- Grid-forming inverter
An inverter that sets its own voltage and frequency reference and can therefore hold a network up alone. A grid-following inverter, the conventional kind, synchronises to an existing voltage and stops when it is lost. Grid-forming batteries supply synthetic inertia and fault current and are replacing the services of retiring synchronous plant. A grid-forming facility battery can hold the site up when the network is lost and be contracted for system strength services.
See also System strength, Inertia, Battery energy storage system
Group 02
Generation and procurement
An AI facility runs at a near-constant load every hour of the year, which is the hardest shape to supply from a grid built around variable renewables. The mix of generation and the structure of the contracts decide the facility's cost per megawatt-hour, its exposure to price spikes and what it can claim about the carbon content of its compute.
- Dispatchable generation
Generation that can be turned up or down on instruction, within its technical limits, at any time: gas, hydro, coal, nuclear and batteries while they hold charge. Dispatchable plant is what the operator calls on when variable output falls short, and it sets the price in most hours. A facility's firmness ultimately rests on dispatchable capacity somewhere: in the grid, under a contract or behind its own meter.
See also Variable renewable energy, Firming, Gas peaking plant
- Variable renewable energyVRE
Generation whose output follows the weather rather than an instruction, principally wind and solar. Its cost per megawatt-hour is low and its availability in any hour uncertain, so its value to a constant load depends on the firming. A PPA with a wind or solar farm buys energy in the farm's shape, and the gap to a flat load is a cost that sits somewhere: the facility's hedging, a retailer's margin or the spot market.
Show in diagramHide diagram
Solar output over one day. The energy under the curve can equal the load's daily energy while matching it in fewer than half the hours. See also Dispatchable generation, Capacity factor, Firming
- Capacity factor
The energy a plant produces over a period divided by what it would have produced at full rating for the whole period. Solar is limited by daylight, wind by weather; nuclear and geothermal run close to their rating. The capacity factor converts a project quoted in megawatts to megawatt-hours, and a flat 100 MW load needs several times 100 MW of wind and solar nameplate to cover its annual energy.
Show in diagramHide diagram
The ratio of the area under the solar curve to the full 250 MW rectangle is its capacity factor for the day. See also Variable renewable energy, Load factor, Megawatt and megawatt-hour
- Baseload
The minimum demand on a system that persists around the clock, and by extension the plant built to run continuously to serve it. System operators use the word less than they did, because modern grids are balanced by flexible plant and storage. For an AI facility the term applies in the other direction: the load itself is baseload shaped, and the supply has to be assembled to match it.
Show in diagramHide diagram
The load line. An AI facility draws close to the same power in every one of the 24 hours. See also Load factor, Dispatchable generation, Firming
- Firming
Making a variable supply reliable by adding something that fills the gaps: storage, dispatchable generation, demand response or a financial contract that pays out when the variable source is short. Most of the cost of renewable supply to a constant load lives here, usually priced separately from the energy. A renewable supply described as firm is backed by physical firming, a contract that settles the difference, or an assurance; the contract should say which.
Show in diagramHide diagram
The firming gap: every hour in which solar plus wind falls short of 100 MW, concentrated from 18:00 to 07:00. See also Variable renewable energy, Battery energy storage system, Contract for difference
- Battery energy storage systemBESS
A grid-scale battery with its inverters, transformers, controls and enclosures, able to charge from and discharge to the network. Lithium-ion chemistry dominates at durations of a few hours. A BESS earns from shifting energy between cheap and expensive hours, from frequency and other ancillary services, and from holding a facility up through short interruptions; one installation can be contracted for several at once, with the facility's own resilience taking priority.
See also Storage power and energy rating, Round-trip efficiency, Grid-forming inverter
- Storage power and energy rating
A battery is specified by power in megawatts, its charge or discharge rate, and energy in megawatt-hours, the amount it holds; their ratio is the duration at full power, so a 100 MW, 200 MWh system is a two-hour battery. Announcements quote whichever number is larger; a battery described by megawatt-hours alone may hold a facility a long time at low rate or briefly at full rate, and the figure that matters is the one matching the gap.
Show in diagramHide diagram
A 100 MW, 200 MWh battery charges from the midday surplus and covers two hours of the evening gap at full power. The other eleven hours remain. See also Battery energy storage system, Round-trip efficiency, Megawatt and megawatt-hour
- Round-trip efficiency
The share of the energy put into a storage system that comes back out, after losses in the cells, inverters, transformers and cooling. Lithium-ion systems return most of what they store; pumped hydro and hydrogen return less. Every megawatt-hour cycled through storage costs more than its purchase price, so a firming strategy that cycles a battery daily should be costed on energy delivered rather than energy bought.
Show in diagramHide diagram
The discharging area is smaller than the charging area. The difference is the round-trip loss. See also Battery energy storage system, Storage power and energy rating
- Gas peaking plant
An open-cycle gas turbine or reciprocating engine plant built to run for a small number of hours a year when demand or prices are high. Peakers are cheap to build and expensive to run, the right trade for low utilisation. Behind a facility's meter the same machines are standby generation, and in some jurisdictions they now firm renewable supply; their emissions in the hours they run are one reason hourly carbon accounting matters.
See also Dispatchable generation, Firming, Behind-the-meter and front-of-meter
- Nuclear and small modular reactorsSMR
Nuclear plant supplies constant, low-carbon power at a high capacity factor, the shape an AI facility wants. Small modular reactors are designs of a few tens to a few hundred megawatts, factory-built and licensed as a type to avoid the construction times of large reactors. Few SMR designs are licensed and fewer operate, so a plan depending on one carries development risk measured in years; in Australia nuclear generation is prohibited under federal law.
See also Dispatchable generation, Capacity factor, Sovereign and jurisdictional constraints on generation
- Co-location with generation
Siting a facility beside a generator or storage asset so that power arrives over a short private connection rather than the shared network. It can avoid network charges, shorten the connection timetable and give first call on the plant's output, but ties availability to one plant and one grid point; in most jurisdictions a network connection is still needed for the hours the plant is down, and the treatment of a private wire varies by market.
Show in diagramHide diagram
Co-location moves the facility to the left end of the chain, beside the generator, and shortens the path to a private wire. See also Behind-the-meter and front-of-meter, Network charges, Firm and non-firm access
- Power purchase agreementPPA
A long-term contract under which a buyer pays for a specific generator's output, or a fixed volume, at an agreed price or formula. PPAs give the generator revenue certainty to finance construction, and the buyer a price hedge and the plant's environmental attributes. The word covers physical, financial and sleeved structures differing in who delivers the energy and who carries shape and volume risk, so read a PPA for structure before price.
Show in diagramHide diagram
Three structures that share one name. They differ in who delivers the energy and who carries the gap between the plant's shape and the load's. See also Physical power purchase agreement, Virtual power purchase agreement, Sleeved power purchase agreement
- Physical power purchase agreement
A PPA under which the generator's energy is delivered to the buyer, over a private wire or through the network with the buyer registered to receive it. The buyer takes title to the energy and usually to the certificates. In a network-delivered physical PPA the buyer or its retailer also handles the difference between what the plant produces each interval and what the facility uses, the shape risk a flat load makes large.
Show in diagramHide diagram
A physical PPA delivers the energy. The facility, or its retailer, carries the difference between what the plant makes and what the site uses in each interval. See also Power purchase agreement, Sleeved power purchase agreement, Hedging
- Virtual power purchase agreementVPPA
A financial contract in which no energy changes hands: the generator sells at spot, the buyer keeps its usual supplier, and the two settle the difference between an agreed price and the spot price at the generator's node or region. The buyer usually gets the certificates and claims the output. The hedge holds to the extent the buyer's purchase price tracks the generator's spot price; the gap when regions or shapes differ is basis risk.
Show in diagramHide diagram
No energy moves between the parties. They settle the difference between the strike and the spot price at the generator's node, and the facility keeps buying as before. See also Power purchase agreement, Contract for difference, Locational marginal pricing
- Sleeved power purchase agreement
A PPA in which a retailer sits between generator and buyer, taking the output, firming it into the buyer's load shape and delivering a single supply contract. The retailer charges a sleeving fee for the shape, volume and balancing risk. It is the most common structure for a large load in the National Electricity Market, where only registered market customers buy directly, and the fee is where the real cost of firming variable output appears.
Show in diagramHide diagram
A retailer takes the plant's output, firms it into the facility's flat shape and charges a sleeving fee for carrying the risk. See also Power purchase agreement, Physical power purchase agreement, Retailer and market customer
- Contract for differenceCfD
A contract that fixes a price for a volume of electricity by settling the difference between a strike and a reference market price each interval: above the strike the seller pays the buyer, below it the buyer pays. CfDs underpin most virtual PPAs and many government renewable schemes, and the hedge is exact only for the contracted volume and shape: a flat-volume CfD against a flat load is clean; one on a solar farm's output leaves the night uncovered.
Show in diagramHide diagram
The dashed two-way arrow is a contract for difference: seller pays when spot is above the strike, buyer pays when it is below. See also Virtual power purchase agreement, Hedging, Merchant exposure
- Take-or-pay
A contract term under which the buyer pays for a minimum volume whether or not it takes it. Such clauses appear in gas supply, some PPAs and network and capacity contracts, moving volume risk to the buyer. For a facility that ramps up over years, an obligation sized for the final load is a cost carried from day one, so connection capacity, energy and gas are often contracted in tranches that follow the fit-out.
See also Power purchase agreement, Load factor, Network charges
- Load-following
Generation or storage that adjusts its output to track a specific load rather than a market signal. A facility islanded on its own generation needs plant that follows the load's swings, and a large training cluster swings sharply when a job starts, stops or pauses to synchronise. Machines that load-follow well cost more per megawatt than those built to run flat, and the controls between generators, batteries and load are where many island-mode designs fall short.
See also Behind-the-meter and front-of-meter, Demand response, Battery energy storage system
- Demand response
A load reducing or shifting consumption on instruction or in response to price, for payment or avoided cost. AI facilities are marketed as flexible because training jobs can in principle pause, but contracted inference cannot and most customer contracts forbid interruption, so the demand on offer is only the part the facility controls. Real demand response earns ancillary service revenue, secures a non-firm connection sooner and can exempt the facility from early shedding.
Show in diagramHide diagram
Demand response lowers the load line in the evening peak. Only the part of the load the facility controls can move. See also Curtailment, Firm and non-firm access, Ancillary services
- Spot and contract markets
The spot market prices and settles electricity each dispatch interval, five minutes in the National Electricity Market and five to sixty minutes elsewhere; the contract market is where that price is hedged through PPAs, contracts for difference, swaps, caps and retail contracts. All physical energy passes through spot and contracts move money around it. A facility's effective price is spot plus the net settlement of its contracts; the portfolio decides the outcome, spot the volatility.
See also Hedging, Merchant exposure, Contract for difference
- Hedging
Reducing spot price exposure by holding contracts whose payouts move against it: fixed-price retail supply, swaps, caps that pay out above a strike, and PPAs. A hedge book is judged by how closely its volume and shape match the load every hour and by its counterparties' credit. A flat load is easy to hedge in principle and costly when the available contracts are shaped by solar output, leaving the evening and winter to be covered.
Show in diagramHide diagram
A solar PPA hedges the hours under the curve. The hatched hours are hedged by something else or by nothing. See also Spot and contract markets, Contract for difference, Merchant exposure
- Merchant exposure
The share of a facility's energy bought at spot with no hedge, or of a generator's output sold at spot with no contract. Some merchant exposure is unavoidable because contracts never match load exactly. Lenders tolerate a limited amount, and a supply plan quoting a low average price should be read for how much volume is merchant and what the price would be in a bad year.
See also Hedging, Spot and contract markets, Firming
Group 03
Electrical plant to the fence
The substation, transformers and switchgear between the network and the fence are the facility's largest single electrical exposure and its longest-lead equipment. A transformer ordered late moves the energisation date by the full length of its lead time, and a fault in this plant takes out the whole site rather than one hall.
- Substation
The installation where voltage is changed and circuits are switched, protected and metered: transformers, switchgear, busbars, protection and control equipment in a secured compound or building. A large facility usually has a dedicated connection substation stepping transmission or sub-transmission voltage down to the site's distribution voltage. The connection agreement sets whether the connecting party or the network owner builds and owns it, which changes programme, cost and who is called when it fails.
Show in diagramHide diagram
The substation compound. Everything inside the dotted line changes voltage, switches circuits and meters energy for one facility. See also Power transformer, Switchgear, Connection assets
- Connection assets
The lines, cables and substation equipment built solely to connect one facility to the shared network. Overhead lines are cheaper and faster per kilometre and more exposed to weather and fire; underground cables cost far more, take longer to repair and are often required near urban land. They are usually paid for by the connecting party, may be contestable, and stay on the facility's side of the boundary even when the network owner operates them.
See also Contestable works, Substation, Point of connection
- Power transformer
The machine that transfers power between two voltage levels through magnetic coupling, with no moving parts beyond its cooling and tap changer. At a facility connection, transformers step the network voltage down in one or two stages to the medium voltage distributed around the site. They are large, custom-built, oil-filled and slow to replace, so the number and rating of transformers, and the spare held on site, is a first-order availability decision.
Show in diagramHide diagram
Two 132/33 kV transformers in parallel. Each is rated to carry the whole site so that one can be out of service. See also Transformer rating and ratio, Transformer lead time, Substation
- Transformer rating and ratio
A transformer is rated by apparent power in megavolt-amperes, voltage ratio, such as 132 kV to 33 kV, and cooling stages, each allowing a higher rating as fans and pumps are added. The MVA figure applies at rated temperature rise; the real power a facility can draw through it is that figure times the power factor. An on-load tap changer adjusts the ratio in small steps to hold secondary voltage steady.
Show in diagramHide diagram
A transformer is rated on the hypotenuse. Its MW capability is the horizontal side, and shrinks as the angle opens. See also Power transformer, Power factor, High, medium and low voltage
- Switchgear
The circuit breakers, disconnectors, earthing switches, busbars and instrument transformers that connect, isolate and protect circuits at a given voltage. High-voltage switchgear is air-insulated in an outdoor yard or gas-insulated in a compact enclosure; medium-voltage switchgear sits in rows of metal-clad panels. Rated current and fault-breaking capacity must exceed the network's fault level at the point, and the busbar arrangement decides whether a failed section can be isolated while the rest stays live.
Show in diagramHide diagram
The 132 kV switchgear: two incomer breakers, a bus-section breaker and two transformer breakers on one busbar. See also Fault level, Protection relay, Radial and ring feeds
- High, medium and low voltage
The conventional bands for electrical plant: low voltage up to 1 kV, medium voltage from 1 kV to about 35 kV in IEC usage and higher in North America, and high voltage above that, with extra-high voltage for the largest transmission lines. Equipment, clearances, safety rules and qualifications change at each boundary. A facility connects at high voltage, distributes at medium and uses equipment at low; each transformation loses energy and adds a failure point.
See also Transformer rating and ratio, Switchgear, Transmission network
- Fault level
The current that would flow at a point if a short circuit occurred there, set by network strength and the transformer impedance between source and fault. It sets the switchgear's fault-breaking capacity and the mechanical forces equipment must bear. A high fault level means a strong network and dearer switchgear; a low one a weak network where voltage dips and power quality are harder to manage. Fault level studies are part of every connection application.
Show in diagramHide diagram
The 132 kV breakers are rated to interrupt the fault current available at this point. A stronger network means a higher rating. See also System strength, Switchgear, Protection relay
- Radial and ring feeds
Two ways of arranging the circuits that supply a site. A radial feed runs from source to load along one path, so any fault interrupts supply until repaired. A ring runs from the source through several points and back, so a faulted section can be isolated and loads beyond it fed from the other side. Rings cost more in cable and switchgear and allow any section to be maintained or lost without an outage.
Show in diagramHide diagram
The 33 kV board with four feeders. Closing the bus-section breaker turns two radial halves into one supplied from either side. See also Dual feeds, Switchgear, N-1
- Dual feeds
Two independent supplies to a site from separate network circuits, ideally from separate substations by separate routes, each able to carry the full load. Dual feeds are the first requirement for high availability at the grid level, and independence is the point: two circuits on the same towers or the same transformer fail together. The connection agreement and planning standard decide whether both feeds are firm and how fast supply transfers between them.
Show in diagramHide diagram
Two incoming 132 kV lines. The independence of their routes and source substations decides whether these are two feeds or one. See also Radial and ring feeds, N-1, Firm and non-firm access
- Protection relay
The device that measures current, voltage and frequency on a circuit, compares them against its settings and trips a circuit breaker when they indicate a fault. Modern relays are digital, record every event and communicate to decide which breaker opens first. Settings are graded so the breaker nearest the fault trips before those upstream, and the grading study proving this against the network owner's protection is a connection requirement.
Show in diagramHide diagram
One relay per breaker, graded so that the breaker nearest a fault opens first. The dashed line is the signalling between them. See also Network protection, Switchgear, Fault level
- Power quality
How closely the voltage supplied to and current drawn by a facility stay to an ideal sine wave at nominal magnitude and frequency, measured as harmonics, flicker, unbalance, sags and swells. Network standards limit what the network must deliver and what a load may cause. AI facilities run on power electronics, so they are both sensitive to poor quality and capable of causing it, and connection studies test the second as closely as the first.
See also Harmonics, Reactive power, Performance standards
- Harmonics
Distortion of the voltage or current waveform by components at multiples of the fundamental frequency, produced by rectifiers, inverters, variable-speed drives and switch-mode power supplies. Harmonic currents heat transformers and cables beyond their fundamental loading, interfere with protection and can pass back into the network. Connection agreements cap the harmonic emission a facility may inject, and filters or active front ends on its equipment are how the cap is met.
Show in diagramHide diagram
Harmonic currents add a third component the triangle does not show. Like reactive power, they load the plant without doing work. See also Power quality, Power factor, Performance standards
- Reactive power
The component of alternating-current power that oscillates between source and load without doing work, measured in megavolt-amperes reactive and needed to magnetise transformers and motors and hold voltage up along lines. It travels poorly, so it is supplied locally by capacitors, synchronous condensers, static compensators or battery inverters. The connection agreement sets the reactive range a facility must absorb or supply at its connection point, sizing equipment it would not otherwise buy.
Show in diagramHide diagram
Reactive power is the vertical side: current that magnetises transformers and holds voltage up, and delivers no energy. See also Power factor, Frequency and voltage, Transformer rating and ratio
- Power factor
The ratio of real power, in megawatts, to apparent power, in megavolt-amperes, at a point in the system. A power factor of one means all the current does useful work; lower values mean conductors and transformers carry current that delivers no energy. Network tariffs penalise poor power factor through demand charges levied in megavolt-amperes, and it consumes transformer capacity, so correction equipment pays for itself quickly in a large facility.
Show in diagramHide diagram
Power factor is the cosine of the angle. At 0.9, the transformer carries 111 MVA to deliver 100 MW. See also Reactive power, Transformer rating and ratio, Demand charge
- Transformer lead time
The time between ordering a large power transformer and receiving it, for transmission-class units now measured in years in most markets. The constraint is a small number of manufacturers, specialised steel and copper supply, and demand from grid replacement programmes and renewables as well as data centres. The order is therefore placed before the connection agreement is final and the facility design frozen, a capital commitment made on incomplete information.
Show in diagramHide diagram
The transformer order runs from under application to under energisation. The dashed section is the part placed before the agreement exists. See also Long-lead items, Power transformer, Network augmentation
- Long-lead items
Equipment whose delivery time exceeds the time between ordering it on firm information and needing it on site: large transformers, high-voltage switchgear, gas turbines, large generators and some cable. Long-lead items set the critical path of a facility programme and are ordered early, often by the sponsor at its own risk, to protect the energisation date. Holding or trading manufacturing slots for this equipment is a real competitive position today.
Show in diagramHide diagram
Long-lead items are ordered on the lower track so that their delivery meets the energisation box rather than following it. See also Transformer lead time, Energisation, Switchgear
- Energisation
The moment the network owner first applies voltage to the facility's connection assets, after the works are complete and inspected and the agreement's conditions precedent are met. It is distinct from commercial operation: equipment is energised in stages, tested under load and released for service afterwards. The energisation date is the figure the revenue model depends on, controlled by the network owner's programme, any augmentation and the long-lead items.
Show in diagramHide diagram
Energisation, the seventh box. The revenue model counts from here, and three tracks have to meet to reach it. See also Grid-side commissioning, Connection offer and agreement, Long-lead items
- Grid-side commissioning
The staged tests that prove the connection and the facility's electrical plant behave as the agreement requires: protection trips, phasing checks, transformer energisation, load steps, reactive capability and harmonic and flicker measurements. In the National Electricity Market the sequence includes hold points the market operator must release and measured data to validate the connection study models. This grid-side programme runs alongside, and sometimes gates, the Data Centre layer's commissioning of the power train inside.
Show in diagramHide diagram
Grid-side commissioning sits between energisation and operation. In the National Electricity Market each stage is released at a hold point. See also Energisation, Performance standards, Metering and settlement
- Metering and settlement
Revenue metering records the energy passing the point of connection each settlement interval, to an accuracy class set by market rules; settlement turns the readings into what the facility pays for energy, network use and market fees. In the National Electricity Market the interval is five minutes and an accredited metering provider, rather than the network owner, supplies the meter. This data underpins every energy cost, carbon and provenance claim the facility makes.
Show in diagramHide diagram
Revenue metering on each incomer. These two meters are the source of every energy, carbon and provenance figure the facility reports. See also Point of connection, Spot and contract markets, Energy provenance evidence
Group 04
Economics and provenance
Energy is the largest operating cost of an AI facility and the one that buyers of compute increasingly ask about. The structure of the bill decides which levers an operator has, and the rules for provenance decide whether a claim of clean power would survive a customer's audit.
- Megawatt and megawatt-hour
A megawatt is a rate, the power drawn or supplied at an instant; a megawatt-hour is a quantity, one megawatt sustained for one hour. Facility capacity, connection rights and transformer ratings are in megawatts; energy purchases, certificates and carbon accounts are in megawatt-hours. The two are routinely confused in announcements, and a site described in megawatts without a load factor says nothing about the energy it will buy or what it will cost.
Show in diagramHide diagram
The horizontal side is power, a rate in MW. Multiplying it by hours gives energy in MWh, the unit the facility is billed in. See also Load factor, Storage power and energy rating, Capacity factor
- Load factor
The average power a facility draws over a period divided by its peak or contracted demand. AI facilities have high load factors because the IT load runs continuously: cheap to cover on energy pricing, costly on network pricing because the facility uses its connection every hour and gains nothing from diversity with other customers. A partly fitted-out facility has a low load factor and pays for capacity it does not yet use.
Show in diagramHide diagram
A flat line has a load factor near one. The same facility half fitted out would sit at 50 MW against a 100 MW connection. See also Megawatt and megawatt-hour, Demand charge, Take-or-pay
- Energy charge
The part of the bill that pays for the electricity itself, priced per megawatt-hour at the spot price, a contract price or a retail tariff. It is the component PPAs, hedges and the generation mix act on. On a large facility's bill it is usually the largest line and the one quoted when a site's power is called cheap, which hides the network and demand charges paid whatever the energy price does.
See also Network charges, Demand charge, Spot and contract markets
- Network charges
Regulated charges for using the transmission and distribution networks, recovered by the network owners through the bill. In Australia they are transmission and distribution use of system charges, set per network under a revenue determination; other markets use terms such as transmission access charges or network tariffs. They are largely fixed by capacity and location, untouched by cheaper energy, and can approach the energy charge itself for a load far from generation.
Show in diagramHide diagram
Network charges pay for the transmission and distribution spans. They do not fall when the energy at the left end gets cheaper. See also Energy charge, Demand charge, Marginal loss factor
- Demand charge
A charge on the facility's peak demand over a period, in megawatts or megavolt-amperes, rather than on the energy it uses. It recovers the cost of the network and generation capacity needed to serve the peak. It is levied on the highest reading in a billing period, sometimes within a daily window, so one short excursion sets the month's charge; peak management, power factor correction and peak-shaving storage all act on this line.
Show in diagramHide diagram
Demand charges levied in MVA bill the hypotenuse. Correcting the power factor shortens it without changing the real power drawn. See also Load factor, Power factor, Network charges
- Marginal loss factorMLF
An Australian mechanism that adjusts the price a participant pays or receives for the electrical losses between its connection point and the regional reference node. A load with a factor above one pays slightly more than the regional price, since energy lost reaching it must still be generated; a remote, congested generator receives less. The market operator recalculates it yearly as flows change, so a remote site's effective price can move without the market moving.
Show in diagramHide diagram
Losses accumulate across each span between the regional reference node and the connection point. The loss factor prices them. See also Network charges, Locational marginal pricing, Spot and contract markets
- Levelised cost of energyLCOE
The average cost per megawatt-hour from a plant over its life, found by dividing the present value of its capital and operating costs by the present value of its output. LCOE compares generation technologies and is the figure behind claims that renewables are the cheapest power. It excludes firming, network connection and the hours the plant does not run, so a solar farm's LCOE understates the cost of supplying a facility from it.
See also Capacity factor, Firming, Marginal cost and merit order
- Marginal cost and merit order
The cost of producing one more megawatt-hour: near zero for wind and solar, mostly fuel for gas, and for a battery the energy bought to charge it plus degradation. Spot markets dispatch plant in order of offered price, the merit order, and the dearest plant needed sets the price. Prices therefore fall towards zero at sunny midday and rise to the cost of gas or the market cap in the evening, which sets a flat load's average.
Show in diagramHide diagram
The price line follows the merit order: near zero when solar sets it at midday, at the cost of gas or the cap in the evening. See also Spot and contract markets, Levelised cost of energy, Gas peaking plant
- Capacity market
A mechanism that pays generators and storage for being available, separately from energy, so enough capacity exists for peak demand. Several North American and European systems run capacity auctions and Western Australia has a reserve capacity mechanism; the eastern National Electricity Market is energy-only with a high price cap. Where one exists, large loads pay capacity charges by their contribution to the system peak, another way a flat load's bill differs from the average.
See also Spot and contract markets, Demand charge, Ancillary services
- Locational marginal pricingLMP
A market design that calculates the spot price at each node of the transmission network, reflecting congestion and losses to the rest of the system. Most North American markets price nodally; the National Electricity Market and most European markets price by region or zone and handle congestion with constraints and loss factors. A facility behind a congested line pays more than one beside generation, which moves siting and makes the settlement node a material PPA term.
See also Marginal loss factor, Virtual power purchase agreement, Spot and contract markets
- Grid carbon intensity
The mass of carbon dioxide emitted per megawatt-hour from a given grid or region, varying by the hour with the generation mix. Annual averages hide a daily cycle in which intensity is low while solar runs and high in the evening when gas and coal set the margin. Reported emissions depend on which intensity is applied, and a flat load's true intensity sits closer to the evening figure than the annual average.
Show in diagramHide diagram
Grid intensity follows the same shape as the price line. A flat load's average intensity is weighted towards the hatched hours. See also Scope 2, location-based and market-based, Annual and hourly matching, Marginal cost and merit order
- Renewable energy certificateREC
A tradeable certificate for one megawatt-hour of renewable electricity, created on generation and retired when a buyer claims the energy. Australia's large-scale generation certificates, Europe's guarantees of origin and North American RECs are variants of the same instrument. The attribute can be sold apart from the electricity, so a claim backed only by certificates covers energy that may have been generated at another time, in another place and sold to someone else.
Show in diagramHide diagram
Certificates travel on their own path in every structure. They can be sold without the energy, which is what makes the claim they support worth checking. See also Annual and hourly matching, Additionality, Scope 2, location-based and market-based
- Annual and hourly matching
Two standards for claiming renewable supply. Annual matching needs certificates equal to the load's annual consumption, whenever generated; hourly matching, often called 24/7 carbon-free energy, needs generation in the same hour on the same grid as each hour consumed. A flat AI load is easy to match annually with solar certificates and hard to match hourly, since night and winter need firm clean supply; the gap between the standards is the firming problem as accounting.
Show in diagramHide diagram
Annual matching nets the midday surplus against the evening shortfall. Hourly matching cannot, and every hatched hour needs its own clean supply. See also Renewable energy certificate, Grid carbon intensity, Firming
- Additionality
Whether a buyer's purchase caused new renewable generation that would otherwise not exist. A PPA signed before a plant reaches financial close is additional; certificates from a plant that has run for years are not. Customers and standards bodies increasingly ask for additionality behind a clean energy claim, and a facility whose supply rests on long-established hydro or wind may find the claim accepted by its accounting method and rejected by its customers.
See also Renewable energy certificate, Power purchase agreement, Energy provenance evidence
- Scope 2, location-based and market-based
The two methods the Greenhouse Gas Protocol requires for reporting emissions from purchased electricity. The location-based method applies the average intensity of the grid the facility sits on; the market-based method applies the intensity of the contracts and certificates it holds, with a residual mix for anything uncovered. A facility can report near-zero market-based emissions on annual certificates while its location-based figure shows the evening gas it drew; both are disclosed side by side.
See also Grid carbon intensity, Renewable energy certificate, Annual and hourly matching
- Power usage effectiveness, seen from the gridPUE
The ratio of the total energy a facility draws at its boundary to the energy delivered to IT equipment. The ratio belongs to the Data Centre layer but is measured at the Power layer's meter; from the grid's side a PUE of 1.2 means a connection and an energy bill a fifth larger than the IT load and IT energy. Connection transformer losses sit outside most PUE boundaries and are paid for all the same.
Show in diagramHide diagram
The connection transformers sit above the facility boundary. Their losses are paid for by the facility and usually fall outside the PUE boundary. See also Megawatt and megawatt-hour, Metering and settlement, Transformer rating and ratio
- Energy provenance evidence
The records that substantiate a claim about where a facility's energy came from: interval meter data, certificate registry retirements, PPA settlement statements, the generator's metered output and, for hourly claims, time-stamped matching of load against generation. A claim without this trail is an assertion. Buyers of sovereign and regulated compute increasingly require the evidence, and assembling it after the fact is far harder than contracting for it at the start.
See also Metering and settlement, Renewable energy certificate, Annual and hourly matching
- Sovereign and jurisdictional constraints on generation
Limits set by law or policy on what can be built, bought or claimed in a jurisdiction: technology prohibitions, such as nuclear generation in Australia, requirements that generation or certificates come from within a country or region, foreign investment review of generation and network assets, and emissions or noise standards for on-site plant. They decide which supply structures are open, so the same facility design carries a different power plan in each country.
See also Nuclear and small modular reactors, Additionality, Renewable energy certificate
- Retailer and market customer
The two ways a large load buys electricity. Through a retailer, the facility holds one contract and the retailer buys wholesale, hedges and pays network charges for a margin. As a registered market customer, a National Electricity Market term with equivalents elsewhere, the facility buys at spot, posts credit support with the market operator and runs its own hedge book. Direct participation removes the margin and puts price, credit and operational risk on the facility.
Show in diagramHide diagram
The retailer box. A registered market customer removes it and buys at spot directly, taking on the hedging and credit support itself. See also Spot and contract markets, Hedging, Sleeved power purchase agreement
Where this leads
What Outpace does with this vocabulary.
The terms of each layer describe the gap between what an asset could do and what it does. Outpace underwrites that gap. The thesis sets out why contracted, productive output matters more than installed capacity.